Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit: TC-SOL-0425-00485

Parcel: 132090700


Addresses:

2826 E RICKEY VISTA

Inspection Status: Partial Pass

Inspection History: BULD - Electrical Clearance

Date Description Inspector Results Comments
05/21/2025 BULD - Electrical Clearance Partial Pass Partial for the Tesla backup switch - DGL Clearance was called into TEP at 11:15am
Pending solar
06/17/2025 BULD - Electrical Clearance Partial Pass 6/17/25
TEP CLEARANCE: INCR, Partial pass, pending solar.
07/23/2025 BULD - Electrical Clearance Re-inspection required 7/23/25 plans and solar app call for 100amp main breaker, has 125. Needs swapped or revision
08/06/2025 BULD - Electrical Clearance Passed 8/6/25
TEP CLEARANCE: DGL/DGC, derate.