Inspection Status: Re-inspection required
Inspection History: COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in.
| Date |
Description |
Inspector |
Results |
Comments |
| 01/16/2025 |
COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. |
|
Re-inspection required |
1/16/25: HVAC registers require blocks on 3 sides, DWV Must be under test, nail plates required throughout at top plates and bottom plates and in wall(plumbing,electrical, mechanical) anything within 1 1/4" of face of stud, seal all penetrations through top plates and vapor barrier throughout, pex must have a 12" clearance from can lights, pressure relief for water heater discharge not roughed in, 18" of copper required before first solder joint at pex, water lines not under pressure. STOPPED INSPECTION MORE ITEMS MAY BE ADDED. |
| 01/22/2025 |
COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. |
|
Passed |
1/22/25 corrections made, no further issues found |