Inspection History Details
Inspection Status: Re-inspection required
Inspection History: BULD - Electrical Clearance
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/05/2025 | BULD - Electrical Clearance | Re-inspection required | 05 FEB 25 Not ready; Plans call for 6 AWG wires, contractor used 8 AWG wires. Please submit revision or use size listed on plan. |
|
| 02/05/2025 | BULD - Electrical Clearance | Re-inspection required | 05 FEB 25 Not ready; Plans call for 6 AWG wires, contractor used 8 AWG wires. Please submit revision or use size listed on plan. |
|
| 09/11/2025 | BULD - Electrical Clearance | Partial Pass | Partial for the 60A meter adapter - DGL Clearance was called into TEP at 9:05 am Pending solar final - NR |
|
| 09/17/2025 | BULD - Electrical Clearance | Deferred | Canceled, tech was involved in car accident. | |
| 09/24/2025 | BULD - Electrical Clearance | Passed | 9.24.2025 Corrections made. Clearance for TEP DGC. |