Inspection Status: Re-inspection required
Inspection History: COT - RSBU - Excavation/Rebar/Zoning
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/18/2026 | COT - RSBU - Excavation/Rebar/Zoning | Re-inspection required | 2-18-26: excavation of footings must extend 12 " below native soil, compact pad throughout, remove all loose debris from footings, install #4 rebar at 32" o.c., A2 Detail 1 calls for #4 verticals at 48" o.c. And they were missing. If this detail is not related to scope of work then remove it from plans. Submit the revision to the city for review/approval. Note: At a glance, the underground DWV does not meet code requirements. Running DWV along footings is not allowed. Ask your designer or architect for solutions. |
|
| 02/20/2026 | COT - RSBU - Excavation/Rebar/Zoning | Re-inspection required (with fee) | 2-20-26: footer at patio (detail 2) does not meet depth requirements. Remove rock/boulder at column footer and remove excess concrete from footer at the southwest end of new addition so that it meets depth requirements as outlined per detail 1. Missing #4 dowels at 32" o.c.-dowels must be installed at the existing concrete-see foundation plan for information. Also, underground plumbing/DWV cannot be installed directly in footings nor was the DWV not completely wrapped-consult with an architect to provide details on how to correct. | |
| 02/25/2026 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Ok to place concrete in footings and slab areas. |