Inspection Status: Canceled
Inspection History: COT - RSOL - Electrical Final Solar Project
| Date |
Description |
Inspector |
Results |
Comments |
| 11/06/2024 |
COT - RSOL - Electrical Final Solar Project |
|
Canceled |
Canceled per contractor |
| 11/15/2024 |
COT - RSOL - Electrical Final Solar Project |
|
Canceled |
Canceled by Dustin |
| 11/19/2024 |
COT - RSOL - Electrical Final Solar Project |
|
Not Ready |
Revised set of plans needed as disconnect and breaker are different sizes, tech had plans from September but city only has August plans. Panel placement and bonding correct, just need revised plans for breaker and disconnect |
| 12/04/2024 |
COT - RSOL - Electrical Final Solar Project |
|
Re-inspection required |
Re inspection required. TEP to set meter |