Inspection History Details
Inspection Status: Re-inspection required
Inspection History: COT - RSME - Mechanical Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/10/2025 | COT - RSME - Mechanical Final | Re-inspection required | Weep screed needs to be 2" above all paved areas and 4" above earth. Provide traffic rated caps for sewer. Add cover plates to receptacles, lighting, and gutter box. Add receptacle at kitchen counter @ 4' to the right of sink and at peninsula. Install hammer arrestor at hot line for dishwasher. Install all plumbing fixtures throughout. Water closets need to be in place and caulked. Panel needs to be labeled. Add non-metallic plumbing to panel schedule. Install anti siphons at hose bibs. Insulte exterior water lines and provide UV protection. Install correct size of fuse for AH. Wall with low voltage lines needs to be installed and finished. Provide ladder for attic access. 6/10/2025 | |
| 06/18/2025 | COT - RSME - Mechanical Final | Re-inspection required | Weep screed needs to be 2" above all paved areas and 4" above earth. Provide traffic rated caps for sewer. Add cover plates to receptacles, lighting, and gutter box. Add receptacle at kitchen counter @ 4' to the right of sink and at peninsula. Install hammer arrestor at hot line for dishwasher. Install all plumbing fixtures throughout. Water closets need to be in place and caulked. Panel needs to be labeled. Add non-metallic plumbing to panel schedule. Install anti siphons at hose bibs. Insulte exterior water lines and provide UV protection. Install correct size of fuse for AH. Wall with low voltage lines needs to be installed and finished. Provide ladder for attic access. 6/10/2025 6/18/25 see previous notes, also attic needs 24 inches unobscured crawlspace for service and service receptacle and lighting moved and installed |