Inspection Status: Partial Pass

Inspection History: BULD - Electrical Clearance

Date Description Inspector Results Comments
02/05/2025 BULD - Electrical Clearance Partial Pass 05 FEB 25
TEP CLEARANCE: INCR, Partial pass pending solar.
02/20/2025 BULD - Electrical Clearance Canceled CA by contractor
03/19/2025 BULD - Electrical Clearance Partial Pass Partial for the 40A meter adapter - DGL Clearance was called into TEP
Pending solar
04/01/2025 BULD - Electrical Clearance Passed Approved solar - DGC Clearance to TEP is required for the solar meter