Permit: TC-RES-0623-05913

Parcel: 138141710


Addresses:

117 W CALLE GARCIA

Inspection Status: Not Ready

Inspection History: COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in.

Date Description Inspector Results Comments
01/03/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Not Ready 10/19/23: plans call for split unit on side of house but gas pack was installed ( need trust calcs to verify that roof can support new unit). Also will need new gas BTU calculations for run to rooftop unit. stackable washer and dryer needs to be revised per plan, electrical panel needs to be revised to new location.

1/03/25, see notes above. revisions were not made.
01/09/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed 01/09/25
Passed
09/11/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Not Ready
10/03/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Re-inspection required 10/3/23: registers need to be blocked on 3 sides, fire foam top plate penetrations throughout house, H25 clips need to be completely nailed off, revise electrical plan to reflect current installation. STOPPED INSPECTION.
10/19/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Re-inspection required 10/3/23: registers need to be blocked on 3 sides, fire foam top plate penetrations throughout house, H25 clips need to be completely nailed off, revise electrical plan to reflect current installation. STOPPED INSPECTION.

10/19/23: plans call for split unit on side of house but gas pack was installed ( need trust calcs to verify that roof can support new unit). Also will need new gas BTU calculations for run to rooftop unit. stackable washer and dryer needs to be revised per plan, electrical panel needs to be revised to new location. Ok to insulate walls only.