Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - RSBU - Excavation/Rebar/Zoning
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/18/2026 | COT - RSBU - Excavation/Rebar/Zoning | Partial Pass | Partial pass for 2F4 footers for Ramada | |
| 09/09/2026 | COT - RSBU - Excavation/Rebar/Zoning | Partial Pass | ||
| 10/20/2026 | COT - RSBU - Excavation/Rebar/Zoning | Re-inspection required | 10/20/26: have architect submit a letter to the city for review/approval showing vertical reinforcement spacing & size for CMU wall at garage lintel. | |
| 10/23/2026 | COT - RSBU - Excavation/Rebar/Zoning | Partial Pass | 10/23/2026 Partial pass, okay to grout. Verified detail in approved plans for CMU garage lintel reinforcement and added reinforcement per plan. Waiting on architect letter to be approved |
|
| COT - RSBU - Excavation/Rebar/Zoning | Scheduled |