Inspection Status: Not Ready
Inspection History: COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in.
| Date |
Description |
Inspector |
Results |
Comments |
| 11/10/2025 |
COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. |
|
Not Ready |
Not ready. Ensure lath is in place. Ensure roof is dry in and roof tile is loaded prior to intermediate. Ensure clip nail inspection is closed out before intermediate. 11/10/2025 |
| 12/09/2025 |
COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. |
|
Re-inspection required |
12-9-25: firefoam penetrations in bedroom behind kitchen, swap out R6 piece of flex for R8 on return, fix tear on flex at north bedroom, electrical not per plans- either submit. Revision showing current layout or run electrical per plans. |
| 12/30/2025 |
COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. |
|
Passed |
|