Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - RSBU - Preslab
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/09/2025 | COT - RSBU - Preslab | Partial Pass | UG Plumbing | |
| 07/25/2025 | COT - RSBU - Preslab | Re-inspection required | 7-25-25: setbacks on west side so not match approved plans. Plans call for 25' setback and there is 23'-submit an updated site plan to the city for review and approval. DWV exposed in trench must be wrapped/sleeved, missing 2-LSTHD14 Simpson hold downs. | |
| 08/13/2025 | COT - RSBU - Preslab | Passed | 8.13.2025 Corrections made. Plans revised. Okay for concrete placement. |