Inspection History Details
Inspection Status: Canceled
Inspection History: COT - RSME - Mechanical Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/19/2024 | COT - RSME - Mechanical Final | Canceled | Canceled per contractor. 9/19/2024 | |
| 10/07/2024 | COT - RSME - Mechanical Final | Canceled | 10/4/24: canceled by contractor no access | |
| 10/08/2024 | COT - RSME - Mechanical Final | Passed | Canceled per contractor. 9/19/2024 10/4/24: canceled by contractor no access 10/8/24: condensate drain requires 90degree and must terminate 6" above grade, insulation required at exterior hose bib, clean outs must be capped and cut to grade. UV coat exterior plastic piping. 10/8/24: corrections made ok for CofO |
|
| 10/08/2024 | COT - RSME - Mechanical Final | Re-inspection required | Canceled per contractor. 9/19/2024 10/4/24: canceled by contractor no access 10/8/24: condensate drain requires 90degree and must terminate 6" above grade, insulation required at exterior hose bib, clean outs must be capped and cut to grade. UV coat exterior plastic piping. |