Inspection Status: Re-inspection required
Inspection History: COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in.
| Date |
Description |
Inspector |
Results |
Comments |
| 03/03/2026 |
COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. |
|
Re-inspection required |
All pipes above ground has to be either schedule 80 or emt. Move smoke detector down along with box for fan to be flushed at drywall stage. Provide nail plates at all that are less than an 1 1/4" from the face of the stud. Add missing receptacle at middle wall from door entry. Provide DWV test. Provide exhaust fan. Move over insta hot provide disconnect box for it. Seal off all top penetrations. Provide clean out at laundry. 3/3/2026 |
| 03/09/2026 |
COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. |
|
Passed |
3-9-26: all corrections made. Residential intermediates approved-okay to continue with construction. |