Inspection Status: Re-inspection required
Inspection History: COT - RSBU - Roof Nailing
| Date |
Description |
Inspector |
Results |
Comments |
| 06/02/2025 |
COT - RSBU - Roof Nailing |
|
Re-inspection required |
6-2-25: no plans on site. Arrived on site at approximately 6:50, contacted contractor at 7:04 and left at 7:23 |
| 06/03/2025 |
COT - RSBU - Roof Nailing |
|
Re-inspection required |
6-3-25: add nails to CS20 straps on south & north sides, add nails to CS20 strapping at posts to beams- 10 nails above /below interconnecting points, all 1/2" shear wall anchors require 3x3" washer plates, add shot pins at marked location, add nails throughout edge/joints at rim board, and nails where overpenetrated sheathing more than 1/8".STOPPED INSPECTION-ADDITIONAL ITEMS MAY BE ADDED. |
| 06/06/2025 |
COT - RSBU - Roof Nailing |
|
Re-inspection required |
6-6-25: add nails to shear walls where over penetrated (southeast area) and at marked areas-see shear wall schedule P2, P4. Add nails to loose shear wall at upstairs west side and nails to sill plate to decking at marked locations, add CS20 with 10 nails above/below interconnecting points on northwest side.Add anchor bolts and 3x3" washer plates to porch shear walls-See Detail S4-Note A for spacing requirements, missing gable bracing at garage& porch -See SD-3-Detail 7. Provide truss calculations on reinspect. |
| 06/10/2025 |
COT - RSBU - Roof Nailing |
|
Passed |
6-10-25: roof nailing approved |