Inspection Status: Canceled

Inspection History: RSBU - Building Final 

Date Description Inspector Results Comments
05/05/2025 RSBU - Building Final  Canceled
05/07/2025 RSBU - Building Final  Re-inspection required 5/7/25: weep screed clearance must be 4" from grade, all exterior plastic piping must be coated, Thermostat shall be no higher than 48" A.F.F, Plastic grommets required at air handler and disconnect in attic.
05/09/2025 RSBU - Building Final  Re-inspection required Garage lighting tied into garage receptacle. 5/9/2025
05/13/2025 RSBU - Building Final  Passed 5/13/25
Pass