Inspection Status: Not Ready
Inspection History: COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in.
| Date |
Description |
Inspector |
Results |
Comments |
| 11/14/2024 |
COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. |
|
Not Ready |
11-14-24, add anchor bolts to marked areas for shear walls, properly nail down shot pins and add some where marked. Okay to proceed with construction. Items requiring correction will be verified at intermediates. |
| 11/26/2024 |
COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. |
|
Partial Pass |
11/26/24 panel has 21 circuits, not 23 as per plans. Needs revised plans or additional circuits added. Other issues corrected on site, partial pass pending panel corrections |
| 11/27/2024 |
COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. |
|
Passed |
11/27/24: Electrician added circuits for hot water heater and home run to master bathroom GFCI. Full pass given. |