Inspection Status: Re-inspection required
Inspection History: RSBU - Building Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/05/2025 | RSBU - Building Final | Re-inspection required | 5/5/25: clean out at driveway missing. SWG meter not installed, Non metallic piping label required at main panel, label for future solar equipment required at main panel, 3” clearance for grade at A/C condenser required, A/C disconnect box most be properly secured and all unused knockouts must be sealed, post tension tag required at hose bib, gate required at CMU wall, thermostat shall be no higher than 48” above finish floor, Garage receptacles must be GFCI, no attic access.STOPPED INSPECTION MORE ITEMS MAY BE ADDED. | |
| 05/09/2025 | RSBU - Building Final | Re-inspection required | 5/9/2025 garage lighting and receptacles are tied into same circuit. Plans call for them to be separate. Provide 30" clearance of height in attic. Ductwork is in the way. | |
| 05/13/2025 | RSBU - Building Final | Passed | 5/13/25 Pass |