Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - RSBU - Exterior/Interior Clips/Sheathing/Framing
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/16/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Not Ready | 5/16/25 Not ready |
|
| 05/19/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Re-inspection required | 5/16/25 Not ready 5/19/25 1. Garage header is missing 1 king stud on each end. 2. Studs are broken at stairs, see marking in red. 3. Fire blocking needed at stringers, see stinger details. |
|
| 05/22/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Re-inspection required | Anchor bolts missing throughout exterior, anchor bolts at shear walls marked note c can be 1'4"oc and require 3x3" washer plates | |
| 05/29/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Re-inspection required | 5-29-25: missing anchor bolts and 3x3" washers at garage shear wall, kitchen shear wall , bedroom 5, and at shear wall at family room. Add nails to garage shear wall along base/mudsill area, anchor bolts at east side of patio need to be replaced-anchor bolts shall be installed no closer than 5/8" to edge of sill plate, add shot pins within 6" of end of plates at interior framing, add anchor bolts to any sill plate at columns.STOPPED INSPECTION-ADDITIONAL ITEMS MAY BE NOTED. | |
| 05/30/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Partial Pass | 5-30-25, partial pass-missing 2 anchor bolts at east garage shear wall and on the west end, anchor bolts must be tightened. Okay to proceed with construction and anchor bolts in question to be checked at intermediates. | |
| 06/02/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | 6/2/25 Pass |