Inspection History Details
Inspection Status: Not Ready
Inspection History: RSBU - Building Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/06/2026 | RSBU - Building Final | Not Ready | 7-6-2026 thermostat should be no higher than 48 inches above finish floor. Made observation during Southwest gas clearance. |
|
| 07/10/2026 | RSBU - Building Final | Re-inspection required | 7/10/26: clean cap at driveway must be properly secured and proper clean out cover required at driveway, No gas meter installed at time of final, PRV requires No more than 6" Above finish grade, weep screed shall not terminate closer than 4" above finish grade, properly anchor clamps at ac electrical whip, GFCI AT KITCHEN COUNTER IMPROPERLY WIRED, Water hammer arrestor label shall be cleaned and legible, Thermostat height shall be no higher than 48" AFF, Dryer vent length required at dryer box, bracket at water heater must be properly installed. Properly secure bracket B-vent at air handler, threshold at garage shall be ADA compliant. | |
| 07/14/2026 | RSBU - Building Final | Not Ready | 07/14/2026 Corrections made. SWG still not connected. |
|
| 07/14/2026 | RSBU - Building Final | Passed | 07/14/2026 Verified gas connection. |