Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - RSBU - Preslab
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/06/2025 | COT - RSBU - Preslab | Partial Pass | 8-6-25: preslab, excavation, reinforcement and setbacks verified per plans. However, the Ufer was relocated to north side of home, so an updated site & electrical plan showing change is required. Submit revision to the city for review -Approval by the city is required prior to issuing letter of completion/ C of O. Okay to pour concrete at own risk. | |
| 09/09/2025 | COT - RSBU - Preslab | Passed | 9-9-25: preslab approved. Note: submit a revised site/electrical plan showing ufer/panel at changed location. |