Inspection Status: Re-inspection required

Inspection History: COT - RSBU - Preslab  

Date Description Inspector Results Comments
05/28/2025 COT - RSBU - Preslab   Re-inspection required 5-28-25, remove loose dirt, debris from footings, compact pad around electrical conduits and on east side.
05/29/2025 COT - RSBU - Preslab   Re-inspection required 5-28-25, remove loose dirt, debris from footings, compact pad around electrical conduits and on east side.
5/29/25: Post tension cables must be properly secured, Footing width not per approved plans, pull end of pt cables shall have no more than 1" exposed cables, stationary end of cables shall have no more than 12" of exposed cables, HD1 turndown not per plans,
05/30/2025 COT - RSBU - Preslab   Passed 5-30-25: preslab, excavation/reinforcement/setbacks approved. Okay to pour concrete.