Inspection Status: Re-inspection required
Inspection History: COT - RSBU - Roof Nailing
| Date |
Description |
Inspector |
Results |
Comments |
| 05/27/2025 |
COT - RSBU - Roof Nailing |
|
Re-inspection required |
5-27-25, add anchor bolts at marked locations, staple T-ply at upstairs south wall at base, add nails sill to decking at marked locations, make corrections to T-ply located at west wall, add shot pins to marked locations and nails to roof sheathing at southwest location. |
| 06/04/2025 |
COT - RSBU - Roof Nailing |
|
Re-inspection required |
6-4-25: Loose roof panels requiring correction had been documented on previous inspection and roof was shingled without approval. Submit a letter to the city for review/approval documenting that all roof nailing was done per plans and meets the 2018 IRC. This must be submitted and approved before a C of O can be issued. |
| 06/16/2025 |
COT - RSBU - Roof Nailing |
|
Re-inspection required |
6-16-25: see previous notes related to |
| 06/20/2025 |
COT - RSBU - Roof Nailing |
|
Passed |
|