Inspection History Details
Inspection Status: Not Ready
Inspection History: RSBU - Building Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/06/2026 | RSBU - Building Final | Not Ready | ||
| 07/07/2026 | RSBU - Building Final | Not Ready | 07/07/2026 Not ready. Need to connect water and sewer and TEP electric power. |
|
| 09/23/2026 | RSBU - Building Final | Canceled | ||
| 09/30/2026 | RSBU - Building Final | Canceled | 09/30/2026 Canceled. |
|
| 10/27/2026 | RSBU - Building Final | Partial Pass | 10-27-2026 Plastic outlet behind AC needs to be painted. Ac pads needs 3" pad clearance. Electrical box is missing a knockout at bottom. Toilet needs to be fully caulked first floor. Correction needed / partial pass. | |
| 10/30/2026 | RSBU - Building Final | Passed | 10/30/2026 Corrections made, all conditions satisfied. |