Inspection Status: Re-inspection required
Inspection History: ENGR Engineering Final
| Date |
Description |
Inspector |
Results |
Comments |
| 09/04/2026 |
ENGR Engineering Final
|
|
Re-inspection required |
Plans show this as a rear drain in lot with drain blocks. Site incorrectly graded. Complete screenwall installation. Paint exposed exterior plastic components. Threshold at Accessible entry non-compliant. |
| 09/09/2026 |
ENGR Engineering Final
|
|
Not Ready |
Conditions that need to be satisfied on permit are not satisfied prior to final inspection . |
| 09/11/2026 |
ENGR Engineering Final
|
|
Re-inspection required (with fee) |
No changes from September 4th Engineering Final other than screen wall being finished. |