Inspection History Details
Inspection Status: Re-inspection required
Inspection History: COT - RSPL - Rough Soil
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/20/2025 | COT - RSPL - Rough Soil | Re-inspection required | 3-20-25, per Contractor, underground plumbing, main water line, and sewer was installed per plans and was holding pressure. However, progress areas were backfilled accidentally. Contractor was given 3 options; submit a letter to the city for review stating construction was done per approved plans and meets the 2018 International Residential Code, uncover work and reschedule or run "snake" in system to verify slope/proper fittings. Contractor will submit the letter and is okay to continue construction at own risk. | |
| 03/25/2025 | COT - RSPL - Rough Soil | Partial Pass | 3/25/25 contractor had copy of letter on site, partial pass pending review and approval from city officials. Ok to proceed at own risk | |
| 04/18/2025 | COT - RSPL - Rough Soil | Passed | 4/17/25 Pass, proceed at own risk. |