Inspection Status: Not Ready

Inspection History: COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in.

Date Description Inspector Results Comments
08/09/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Not Ready 8/9/24: No plans on site. Please reschedule the inspection.
COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Not Ready 8/13/24: not ready needed framing inspection
09/17/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Partial Pass Partial for the hot and cold water lines only, okay to continue with intermediates
09/27/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Re-inspection required 8/9/24: No plans on site. Please reschedule the inspection.
8/13/24: not ready needed framing inspection
9/17/24 - Partial for the hot and cold water lines only, okay to continue with intermediates
9/27/24: called Robert at 2:18pm no answer. No access to site
10/01/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Partial Pass Electric and plumbing are Ok; need mechanical to be installed.
10/09/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Re-inspection required 8/9/24: No plans on site. Please reschedule the inspection.
8/13/24: not ready needed framing inspection
9/17/24 - Partial for the hot and cold water lines only, okay to continue with intermediates
9/27/24: called Robert at 2:18pm no answer. No access to site
10/8/24: Properly secure NM 12" from box, NM cable must be properly inserted in box fixture, penetrations through top plate must be properly sealed, penetration through exterior vapor barrier must be sealed, 4 mini split heads called out on plans only 3 installed, exhaust fan must properly terminate to exterior, all metallic boxes must be grounded, electrical panel must be installed at time of intermediate inspection, revise wire size throughout, dryer vent not installed, 18" of copper required at transition from pex to copper. Vents require strap mid-way. Access panel must be framed for A.V.V at laundry.
11/06/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed Corrections were made. Approved. 11/6/2024