Permit: TC-COM-1225-02297

Parcel: 140290290


Addresses:

3301 E GLOBAL LP

Inspection Status: Re-inspection required

Inspection History: COT - LCBU - Masonry Pregrout 

Date Description Inspector Results Comments
05/11/2026 COT - LCBU - Masonry Pregrout  Re-inspection required 5-11-26: called point of contact at 1025 & at 1203 pm. Arrived on site at 1158 hours, waited 10 minutes and left at 1208. I was unable to locate your approved plans and could not view them from tablet. Please reschedule at your convenience.
05/28/2026 COT - LCBU - Masonry Pregrout  Partial Pass 5-28-26: reinforcement at the south CMU wall of " facilities " verified per plans. Okay to grout 1st lift at 4'. 3rd party verified reinforcement at the north wall 4-8', west wall 4-8', south wall 0-4'.
06/02/2026 COT - LCBU - Masonry Pregrout  Partial Pass 6-2-26: reinforcement for cmu south wall at facilities room verified per plans. Okay to grout 2nd lift at 8'
06/03/2026 COT - LCBU - Masonry Pregrout  Partial Pass 6-3-26: reinforcement at cmu walls of facilities room together with lintel/bond beam verified per plans. Okay to grout top out at 12'.
06/09/2026 COT - LCBU - Masonry Pregrout  Passed 6-9-26: top out at facilities room approved.
06/11/2026 COT - LCBU - Masonry Pregrout  Passed 6-11-26: masonry pre grout at "facilities" cmu walls previous inspected all lifts/top out.