Inspection Status: Re-inspection required
Inspection History: COT - LCBU - Masonry Pregrout
| Date |
Description |
Inspector |
Results |
Comments |
| 05/11/2026 |
COT - LCBU - Masonry Pregrout |
|
Re-inspection required |
5-11-26: called point of contact at 1025 & at 1203 pm. Arrived on site at 1158 hours, waited 10 minutes and left at 1208. I was unable to locate your approved plans and could not view them from tablet. Please reschedule at your convenience. |
| 05/28/2026 |
COT - LCBU - Masonry Pregrout |
|
Partial Pass |
5-28-26: reinforcement at the south CMU wall of " facilities " verified per plans. Okay to grout 1st lift at 4'. 3rd party verified reinforcement at the north wall 4-8', west wall 4-8', south wall 0-4'. |
| 06/02/2026 |
COT - LCBU - Masonry Pregrout |
|
Partial Pass |
6-2-26: reinforcement for cmu south wall at facilities room verified per plans. Okay to grout 2nd lift at 8' |
| 06/03/2026 |
COT - LCBU - Masonry Pregrout |
|
Partial Pass |
6-3-26: reinforcement at cmu walls of facilities room together with lintel/bond beam verified per plans. Okay to grout top out at 12'. |
| 06/09/2026 |
COT - LCBU - Masonry Pregrout |
|
Passed |
6-9-26: top out at facilities room approved. |
| 06/11/2026 |
COT - LCBU - Masonry Pregrout |
|
Passed |
6-11-26: masonry pre grout at "facilities" cmu walls previous inspected all lifts/top out. |