Inspection Status: Partial Pass
Inspection History: COT - LCME - Mechanical Intermediate
| Date |
Description |
Inspector |
Results |
Comments |
| 05/06/2026 |
COT - LCME - Mechanical Intermediate |
|
Partial Pass |
5-6-26: schedule this inspection when ready for above ceiling. |
| 05/18/2026 |
COT - LCME - Mechanical Intermediate |
|
Partial Pass |
5/18/2026 Partial pass. Southwest training room 315, office 314,313,312, facilities office 412 supply needs to be set, return required. Office 413. Okay to proceed other progress areas. |
| 05/26/2026 |
COT - LCME - Mechanical Intermediate |
|
Re-inspection required |
5-26-26: electrical & mechanical above ceiling at room's 905 mechanical not completed, room 903 flex duct constricted-add supports at 4' intervals, room 902, room 910 add duct support, room 909 duct support and missing return air, room 908 junction boxes need covers/labeling, room 907 duct support and ripped duct, rm 906 zip tied electrical conduit to seismic light wire-add its own independent support and tape ripped air duct. Tape any tears to HVAC trunks. |
| 06/02/2026 |
COT - LCME - Mechanical Intermediate |
|
Partial Pass |
6-2-26: electrical intermediates, mechanical above ceiling, & mechanical intermediates at room's 906-901 & 905-901 approved. Okay to continue with construction at progress areas. |
| 06/05/2026 |
COT - LCME - Mechanical Intermediate |
|
Partial Pass |
6-5-26: verified return & supply at room's 801, 802, 803, 804, 805, 806, 707, 810, 808, 807. |
| 06/24/2026 |
COT - LCME - Mechanical Intermediate |
|
Partial Pass |
6-24-26: electrical/mechanical intermediates and above ceiling at room's 812, 813, 815, 816, 705-open knockouts on 3 above ceiling junction boxes, missing section of insulation on round duct, missing junction box labelling, 702-work up junction boxes |
| 06/26/2026 |
COT - LCME - Mechanical Intermediate |
|
Partial Pass |
6-26-26: electrical/mechanical intermediates and above ceiling at room's 812, 813, 815, 816, 705,702 approved. Okay to continue with construction at progress areas. |
| 07/10/2026 |
COT - LCME - Mechanical Intermediate |
|
Canceled |
Canceled per contractor. 7/10/2026 |
| 07/30/2026 |
COT - LCME - Mechanical Intermediate |
|
Passed |
7-30-26: mechanical intermediates approved. |