Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - LCME - Mechanical Above Ceiling
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/18/2026 | COT - LCME - Mechanical Above Ceiling | Partial Pass | 5/18/2026 Partial pass. Southwest training room 315, office 314,313,312, facilities office 412 supply needs to be set, return required. Office 413. Okay to proceed other progress areas. | |
| 05/21/2026 | COT - LCME - Mechanical Above Ceiling | Partial Pass | 5-21-26: verified supply at room room 412. Note: flex requires supports at 4' intervals, tape all tears and reschedule inspection on office areas when ready. |
|
| 06/02/2026 | COT - LCME - Mechanical Above Ceiling | Partial Pass | 6-2-26: electrical intermediates, mechanical above ceiling, & mechanical intermediates at room's 906-901 & 905-901 approved. Okay to continue with construction at progress areas. | |
| 06/05/2026 | COT - LCME - Mechanical Above Ceiling | Re-inspection required | 6-5-26: 803, 804, 805, 806, 807, 808, 707-properly tape flex to round duct at north end of room, 810- tape insulation to round duct, 802-add tape to tear at trunk, 801. Check other rooms and add supports to duct at 4' intervals and supports with 2' of a bend. Reschedule inspection so that we may verify corrections. | |
| 06/15/2026 | COT - LCME - Mechanical Above Ceiling | Partial Pass | 6-15-26: electrical/ mechanical above ceiling at room's 812-seal tear on flex, missing junction box lids/labeling 813-seal tears on flex, missing junction box lids/labeling 815, missing junction box lids/labeling, seal tears at flex, 816, 707-open knockouts at junction boxes, install plastic bushings to protect low voltage at junction box, missing lids & labeling. | |
| 06/24/2026 | COT - LCME - Mechanical Above Ceiling | Partial Pass | 6-24-26: electrical/mechanical intermediates and above ceiling at room's 812, 813, 815, 816, 705-open knockouts on 3 above ceiling junction boxes, missing section of insulation on round duct, missing junction box labelling, 702-work up junction boxes | |
| 06/26/2026 | COT - LCME - Mechanical Above Ceiling | Partial Pass | 6-26-26: electrical/mechanical intermediates and above ceiling at room's 812, 813, 815, 816, 705,702 approved. Okay to continue with construction at progress areas. | |
| 07/10/2026 | COT - LCME - Mechanical Above Ceiling | Canceled | Canceled per contractor. 7/10/2026 | |
| 07/30/2026 | COT - LCME - Mechanical Above Ceiling | Passed | 7-30-26: mechanical above ceiling approved. |