Permit: TC-COM-1225-02297

Parcel: 140290290


Addresses:

3301 E GLOBAL LP

Inspection Status: Partial Pass

Inspection History: COT - LCEL - Electrical Intermediate

Date Description Inspector Results Comments
05/01/2026 COT - LCEL - Electrical Intermediate Partial Pass 5/1/26: Electrical in-wall approved @ GL A-F/1-8, GL A.1-B.1/8.5-9.5, GL B1-E/10.5-11.5
05/06/2026 COT - LCEL - Electrical Intermediate Partial Pass 5-6-26: Clarification from G. Armenta is required to determine extent of previous in wall inspection together with courtesy inspections he may have completed.
05/18/2026 COT - LCEL - Electrical Intermediate Partial Pass 5/18/2026 Partial pass. Southwest training room 315, office 314,313,312, facilities office 412 supply needs to be set, return required. Office 413. Okay to proceed other progress areas.
05/26/2026 COT - LCEL - Electrical Intermediate Partial Pass 5-26-26: in wall electrical at room's 902, 903, 910, 909, 908, 907, 906 approved.
06/02/2026 COT - LCEL - Electrical Intermediate Partial Pass 6-2-26: electrical intermediates, mechanical above ceiling, & mechanical intermediates at room's 906-901 & 905-901 approved. Okay to continue with construction at progress areas.
06/05/2026 COT - LCEL - Electrical Intermediate Partial Pass 6-5-26: electrical intermediates at in wall for 801, 802, 803, 804, 805, 806, 707, 810, 808, 807 approved.
06/11/2026 COT - LCEL - Electrical Intermediate Partial Pass 6-11-26: electrical intermediates & framing at facilities' room approved. Okay to insulate walls.
06/24/2026 COT - LCEL - Electrical Intermediate Partial Pass 6-24-26: electrical/mechanical intermediates and above ceiling at room's 812, 813, 815, 816, 705-open knockouts on 3 above ceiling junction boxes, missing section of insulation on round duct, missing junction box labelling, 702-work up junction boxes
06/26/2026 COT - LCEL - Electrical Intermediate Partial Pass 6-26-26: electrical/mechanical intermediates and above ceiling at room's 812, 813, 815, 816, 705,702 approved. Okay to continue with construction at progress areas.
07/10/2026 COT - LCEL - Electrical Intermediate Canceled Canceled per contractor. 7/10/2026
07/30/2026 COT - LCEL - Electrical Intermediate Passed 7-30-26: electrical intermediates approved.