Inspection Status: Re-inspection required
Inspection History: COT - LCBU - Building Final
| Date |
Description |
Inspector |
Results |
Comments |
| 08/19/2026 |
COT - LCBU - Building Final |
|
Re-inspection required |
8-19-26: See electrical final notes. Schedule all remaining inspections and submit any pending reports to the city for review. |
| 08/24/2026 |
COT - LCBU - Building Final |
|
Partial Pass |
8/24/2026 Partial pass. Pending air and balance report. Note: one unit is down a letter will be submitted for the meantime prior to the correction that has to be made. Okay to apply for level 4 TCO. |