Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Building Progress
Permit Number - TC-COM-1224-02387
Inspection Description - COT - HCBU - Building Progress
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/08/2026 | COT - HCBU - Building Progress | Partial Pass | 1-8-26: drywall screw inspection room's 324, 323, 322, 321, 313-missing section of drywall above ceiling at hallway, 312, 311-drywall missing at window approved. Okay for tape & texture progress areas but reschedule inspection for room's 311 & 313 when ready. | |
| 01/20/2026 | COT - HCBU - Building Progress | Partial Pass | 1-20-26: shower test for Section A, 1st. Floor. Okay to continue with construction in all rooms with the exception of Room's 101, 128, and 125 which were not ready. | |
| 01/23/2026 | COT - HCBU - Building Progress | Partial Pass | 1-23-26: drywall screw inspection at room's 216, 217, 218, 215, 214, 219, 220-finish drywall at bedroom soffit. Okay to continue with tape & texture at progress areas. | |
| 01/28/2026 | COT - HCBU - Building Progress | Partial Pass | 1-28-26: drywall screw inspection-room's 224, 211, 212, 223, 222, 213, 221. Okay to tape & texture drywall. | |
| 02/02/2026 | COT - HCBU - Building Progress | Partial Pass | 2.2.26 Screw inspection at shear for: 301 328 327 308 326 309 325 310 Also verified dead space drywall screw inspection at stairwells. Okay to tape & texture progress areas. |
|
| 02/13/2026 | COT - HCBU - Building Progress | Partial Pass | 2-13-26: intermediate reinspect units 121-124 111-115 approved. Add nails at south stairwell per schedule at each level. North stairwell dead space approved. Okay to cover,progress areas. | |
| 02/18/2026 | COT - HCBU - Building Progress | Partial Pass | 2-18-26: drywall nailing for Room A14-East wall only, 201, 202, 207, 206, 203, 204. Okay for tape & texture. | |
| 02/19/2026 | COT - HCBU - Building Progress | Not Ready | 2-19-26: reschedule inspection. Note: I can only inspect a total of 7 units at any given time. | |
| 02/20/2026 | COT - HCBU - Building Progress | Canceled | 2-20-26: canceled by contractor. | |
| 02/23/2026 | COT - HCBU - Building Progress | Partial Pass | Partial pass. West center stairwell. Interior drywall shear approved. Okay to proceed progress areas. 2/23/2026 | |
| 05/16/2025 | COT - HCBU - Building Progress | Partial Pass | 5/16/25: PRE-CON MEETING. | |
| 05/29/2025 | COT - HCBU - Building Progress | Not Ready | ||
| 12/29/2025 | COT - HCBU - Building Progress | Re-inspection required | 12-29-25: drywall shear inspection on room's 314-320. Add screws 7" o.c. Field and along edges. Add screws where screws are 3/8" from edges/joints and cannot over penetrate more than 1/32". |