| 02/11/2026 |
COT - HCME - Mechanical Progress |
|
Partial Pass |
2-11-26: MEP' s at room's 121, 113, 122, 123-seal penetrations at marked locations, add Boca plates in restroom, 112-add bank plate marked locations,111-fire foam at top plate subpanel, 124. Fire foam penetrations in majority of units where hvac line sets penetrate exterior walls, and fix broken or damaged decking areas marked with an X.Okay to cover soffits on south side up to 121. Drywall screw inspection room's 210, 226, 209, 226, 208-okay to tape & texture progress areas but reschedule MEP's to verify corrections. |
| 02/18/2026 |
COT - HCME - Mechanical Progress |
|
Re-inspection required |
2-18-26: MEP's for room 110, 125, 109, 126, 108-penetrations at party wall, 127, 128. Seal/firefoam all mechanical line set penetrations. Will need to verify corrections prior to drywall. |
| 02/19/2026 |
COT - HCME - Mechanical Progress |
|
Re-inspection required |
2-19-26: 108-penetrations at partywall not sealed/hvac line set not sealed at exterior wall, 125-hvac line set at exterior wall not sealed, 127-hvac line set at exterior wall not sealed, 109-same (line set not sealed) , 110-same(line set not sealed). Okay to continue with construction at rooms not listed above but reschedule the others. |
| 02/20/2026 |
COT - HCME - Mechanical Progress |
|
Partial Pass |
2-20-26: MEP's 3rd floor common area room's C01, C02, C03 approved. Okay to continue with construction at progress areas. |
| 02/23/2026 |
COT - HCME - Mechanical Progress |
|
Canceled |
2/23/2026 canceled per contractor. |
| 02/24/2026 |
COT - HCME - Mechanical Progress |
|
Partial Pass |
2-24-26: MEP's 108-110, 124-128 , B01, B02, B03 approved. Okay to continue construction at progress areas |
| 02/25/2026 |
COT - HCME - Mechanical Progress |
|
Partial Pass |
2-25-26: MEP's for room's 105, 104, 106, 103, 107-drafstop missing, 102, 101-strap DWV south wall. With the exception of room's 101 & 107, the remaining rooms are okay to continue with construction at progress areas. |
| 02/27/2026 |
COT - HCME - Mechanical Progress |
|
Not Ready |
2-27-26: not ready. |
| 03/11/2026 |
COT - HCME - Mechanical Progress |
|
Not Ready |
3-11-26: not ready. |
| 03/19/2026 |
COT - HCME - Mechanical Progress |
|
Canceled |
3/19/2026 canceled per contractor. |
| 03/26/2026 |
COT - HCME - Mechanical Progress |
|
Partial Pass |
3-26-26: soffit framing together with MEP's at common area lounges B03 & C03 approved. Okay to drywall progress areas. |
| 04/01/2026 |
COT - HCME - Mechanical Progress |
|
Re-inspection required |
4-1-26: MEP's at common areas laundry room B09, B07, B08, C07, C09, C08. Fire foam all penetrations any horizontal penetrations & at top plates. Areas in question have been marked. Will look at again prior to installation of drywall. |
| 04/02/2026 |
COT - HCME - Mechanical Progress |
|
Partial Pass |
4-2-26: MEP's for B09,B07,C07,C09,C08 approved. Okay to continue with construction at progress areas. |