Inspection History Details
Inspection Status: Re-inspection required
Inspection History: COT - HCPL - Plumbing Intermediate
Permit Number - TC-COM-1224-02387
Inspection Description - COT - HCPL - Plumbing Intermediate
Inspection Status - Re-inspection required
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/09/2026 | COT - HCPL - Plumbing Intermediate | Re-inspection required | 1-9-26: MEP's for 2-floor, Section B- Units 220- adjust/move or add receptacle at kitchen wall (receptacles are required to be installed within 30" of the stove at each side). 219-fire foam penetration at top plate above stove, fire foam horizontal penetration at same area-party wall, fire foam penetration above window, fire foam penetration at top plate restroom, 218-strap DWV, fire foam penetration at top plate. Fire foam all horizontal penetrations at party walls and all vertical penetrations where coil straps penetrate floors. Apply wool at restroom DWV's or fire foam penetrations at top plates in all units. Provide size of smart electrical box above ceiling in hallways to verify box fill. Reschedule inspection for MEP's when ready. | |
| 01/13/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | Section B, Level #2: Room units 211 - 224. Ok to insulate and sheet rock interior walls. | |
| 01/20/2026 | COT - HCPL - Plumbing Intermediate | Canceled | 1-20-26: canceled by contractor. | |
| 01/21/2026 | COT - HCPL - Plumbing Intermediate | Re-inspection required | 1/21/26: M.E.P inspections conducted (in unit# 310,325,309,326,308,327,328), properly support NM cable at chase near restrooms, seal all penetrations through top plates/draft stop/corridor wall, Properly insulate all hot water piping 3/4" or larger, properly seal all rated assemblies at mechanical areas in hallways, receptacle spacing in bedroom in unit 325 shall be spaced not greater than 12', properly secure all dryer vent ducts in-wall, properly seal all openings at chase near restrooms, nail plates required throughout where electrical/plumbing come within 1 1/4" from face of stud, seal penetration near water closet at all bathrooms, | |
| 01/22/2026 | COT - HCPL - Plumbing Intermediate | Canceled | 1-22-26: canceled by contractor. | |
| 01/23/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 1-23-26: reinspected MEP's at room's 310,325,309,326,308,327,328. All corrections made-okay to continue construction at progress areas. | |
| 01/28/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 1-28-26: MEP's at room's 301, 302, 307,306, 303-staple electrical, 304- fire foam/firecaulk penetrations along the east side wall party wall , 305- seal penetration at restroom penetration top plate at dwv. Add grounding screws to all metal pancake boxes in all rooms. Okay to continue construction at progress areas but listed above items need a reinspect prior to covering. | |
| 01/30/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 1-30-26: MEP's 2nd floor, room's 228, 227, 208, 226, 209, 210, 225 verified per plans. Okay to continue with construction at progress areas. | |
| COT - HCPL - Plumbing Intermediate | Scheduled | |||
| 10/24/2025 | COT - HCPL - Plumbing Intermediate | Partial Pass | 10/24/25: Section B drain waste and vent inspection(pressure test approved) 1,2,3 floor | |
| 11/14/2025 | COT - HCPL - Plumbing Intermediate | Partial Pass | 11-14-25: DWV Section A inspection floors 1-3 ( pressure test approved).Room's 128, 228, 328 ADA Showers not tested due to truss in way-pending engineers fix. Okay to continue with construction at progress areas. | |
| 11/19/2025 | COT - HCPL - Plumbing Intermediate | Partial Pass | 11/19/2025 Section B tub inspection levels 2 and 3. Approved. | |
| 11/21/2025 | COT - HCPL - Plumbing Intermediate | Partial Pass | 11-21-25: partial pass on Section B-level 1 tub inspection. DWV at Room's 111, 121, 124 were not wrapped protecting them from pourbqck. Cut back concrete to where DWV is exposed and properly wrap to avoid future damage of piping. | |
| 12/12/2025 | COT - HCPL - Plumbing Intermediate | Partial Pass | 12/12/2025 partial pass. Section B third floor 7 units approved. Okay to proceed progress areas. | |
| 12/15/2025 | COT - HCPL - Plumbing Intermediate | Partial Pass | 12-15-25: Section B, 3RD Floor unit's 321, 313, 322, 312, 323-secure pex lines at tub, add Boca plate for toilet line and firefoam penetration, secure flex in soffit, 311-secure pex lines, firefoam penetration behind tub, Boca plate needed at 3" DWV for toilet line and firefoam penetration, 324-secure pex line at bathroom, add Boca plate for 3" dwv and firefoam penetration. Secure/support all HVAC cabling and copper lines in every unit. Okay to continue construction at progress areas but will have to verify corrections at units. | |
| 12/19/2025 | COT - HCPL - Plumbing Intermediate | Re-inspection required | 12-19-25: 313-penetration not fire foam at DWV in restroom, secure hvac whip, awg penetration in chute and foam penetration at decking, 322-penetration at restroom dwv not fire foamed, secure hvac whip and awg in chute, 323-fire foam penetration at hvac chute-secure hvac whip and fire foam penetration at dwv at restroom, 311-fire foam penetration at dwv in restroom top plate, secure hvac whip, fire foam penetrations at hvac chute top plate/decking, 312-secure hvac whip and fire foam wag in hvac chute, 324-secure hvac whip, fire foam awg penetration at decking/top plate in chute. | |
| 12/23/2025 | COT - HCPL - Plumbing Intermediate | Partial Pass | 12-23-25: 3rd floor plumbing intermediate reinspect for room's 311, 312, 313, 322, 324 approved. Okay to continue with construction at progress areas. |