| 05/04/2026 |
COT - HCEL - Electrical Underground |
|
Not Ready |
5-4-26: not ready-trench depth on 1" schedule 40 must be 18" min. |
| 05/05/2026 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
5-5-26: verified trench depth of 18" for 5-1" Schedule 40 electrical conduits for EV Chargers at the north side. Conduits run from east end to west-okay to backfill approximately 80' of open trench using shading materials. |
| 05/06/2026 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
5-6-26: excavation/ reinforcement for light pole cage in front of trash enclosure approved to pour. |
| 05/07/2026 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
5-7-26: excavation/reinforcement on light pole cage south of pergola verified per revision. Please submit revision to the city for review-okay for concrete placement at own risk. |
| 05/11/2026 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
5-11-26: verified trench depth on 2-1 1/2 & 2-2" Schedule 40 electrical conduits. The conduits are located at the north east end and run west approximately 50'. Conduits are for solar and light pole cages-okay to backfill progress areas using shading materials. |
| 05/18/2026 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
5/18/2026 1” schedule 40 conduit at 24” depth. West end of courtyard. Running and tied into light pole bases. Okay to backfill all progress areas. Shading required. |
| 05/21/2026 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
5-21-26: 3-1' schedule 40 EV conduits along court yard, 1-1" light trench near trash enclosure, 1-1 1/2", 9-1" together with 2-2" schedule 40 electrical conduits for EV chargers running north to south along east end of site. Okay to backfill progress areas using shading materials. |
| 05/22/2026 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
5-22-26: approximately 60' of trench depth verified for a 1" light pole schedule 40 conduit running north to south on east side of driveway near trash enclosure. Reinforcement/excavation for same light pole cage approved- okay for concrete placement. |
| 05/27/2026 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
5-27-26: reinforcement/excavation on 1 light pole at court yard together with another at the northeast corner of site verified per plans. 3-1" schedule 40 conduits for EV chargers running north to south at the courtyard approved. Okay to backfill progress areas and pour the light pole cages. |
| 05/28/2026 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
5-28-26: reinforcement/excavation for 2 light pole cages on west side of building verified per plans. Okay to backfill approximately 140' of open trench for a 1" schedule 40 electrical conduit and okay to pour cages. |
| 05/29/2026 |
COT - HCEL - Electrical Underground |
|
Canceled |
5-29-26: canceled by contractor. |
| 06/04/2026 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
6-4-26: reinforcement/excavation for 2 light pole cages located on north side of site verified per plans-Okay for concrete placement. Verified trench depth at 18" for a 1" Schedule 40 electrical conduit for cages and a 1" Schedule 40 electrical conduit for a Monument Sign- all located at north end. Okay to backfill approximately 110' of trench using shading materials. |
| 06/11/2026 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
6-11-26: verified schedule 40 electrical conduits for site lighting together with conduit for ev chargers along the north and northeast corners of building. Okay to backfill progress areas using shading materials. |
| 06/23/2026 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
6-23-26: reinforcement/excavation for the light pole cage located on the southeast corner of site. Okay for concrete placement. |
| 07/30/2025 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
7/30/25: electrical underground approved from elevator 16' run to the outside of building east end Area A |
| 08/04/2026 |
COT - HCEL - Electrical Underground |
|
Not Ready |
Light pole base north side not ready. Clean footing. Loose fill. Provide 3" minimum. 8/4/2026 |
| 08/21/2025 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
8-21-25: partial pass -UFER /grounding 3/0 copper attached to rebar through Area A. |
| 12/04/2025 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
12-4-25: verified 4-4" schedule 40 electrical secondary conduits from transformer to SES 3 at section b. Okay to backfill progress areas. |
| 12/09/2025 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
12-9-25: verified 4-4" schedule 40 electrical conduits for SES 2 located on northeast side of building. |