Inspection History Details
Inspection Status: Canceled
Inspection History: BULD - Electrical Clearance
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/27/2026 | BULD - Electrical Clearance | Canceled | 3-27-26: canceled by contractor. | |
| 04/22/2026 | BULD - Electrical Clearance | Re-inspection required | 4-22-26: Install metallic addressing labels for each unit, provide plastic bushings to protect awg wires (feeders) at sub panels, install metallic addressing labels at each subpanel. Make sure bonding/grounding is complete per SES details. Provide torque specifications and submit report as an attachment to the city for review. | |
| 04/24/2026 | BULD - Electrical Clearance | Partial Pass | 4-24-26: Okay to meter SES1 to energize Panel 1A. | |
| 04/27/2026 | BULD - Electrical Clearance | Canceled | 4-27-26: canceled by contractor. | |
| 04/30/2026 | BULD - Electrical Clearance | Partial Pass | 4/30/26: ECO TEP CLEARANCE FOR 6675 S 12TH SES1 OWNR | |
| 05/05/2026 | BULD - Electrical Clearance | Partial Pass | 5-5-26: okay to energize SES3 & unit's 311, 312, 313, 314, 315, 316, 317, 318, 319, 320, 321, 322, 323, 324. ECO clearance issued to TEP. NOTE: verified ground-okay to pour back. |
|
| 05/06/2026 | BULD - Electrical Clearance | Partial Pass | 5-6-26: okay to energize unit's 211, 212, 213, 214, 215, 216, 217, 218, 219, 220, 221, 222, 223, 224. ECO clearance issued to TEP. | |
| 05/18/2026 | BULD - Electrical Clearance | Re-inspection required | 5/18/2026 ensure to add duct seal at entry of cables along with ko seals at 111/112 |