Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Excavation/Rebar/Zoning
Permit Number - TC-COM-1224-02387
Inspection Description - COT - HCBU - Excavation/Rebar/Zoning
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/27/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 6/27/25: Third party inspector passed reinforcement for lower floor slab and sump pit for building elevator Detail S3.02/4, elevator pit concrete walls reinforced per plan. | |
| 08/07/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 8/7/2025 area B okay for concrete placement. | |
| 08/25/2025 | COT - HCBU - Excavation/Rebar/Zoning | Re-inspection required | 8-25-25: not ready-missing reinforcement at several areas. SEE S1.0A-Details 3 & 2. | |
| 08/28/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 8.28.25: Area A ok for concrete placement. | |
| 09/25/2025 | COT - HCBU - Excavation/Rebar/Zoning | Canceled | 9-25-25: canceled by contractor. | |
| 09/29/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 9-29-25: reinforcement at elevator equipment room verified at #5 -24" o.c.. lift at 6'- 3rd party inspection report presented. | |
| 09/30/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 9-30-25: top out at elevator equipment room at 9'-okay to grout. |