Inspection Status: Not Ready
Inspection History: ENGR Engineering Final
| Date |
Description |
Inspector |
Results |
Comments |
| 09/23/2026 |
ENGR Engineering Final
|
|
Not Ready |
West Sidewalk needs to be complete for TCO level 4. Site needs to be complete, clear of materials, heavy equipment and safe. Unsatisfied conditions need to be approved for full pass of final. |
| 09/24/2026 |
ENGR Engineering Final
|
|
Not Ready |
|
| 09/25/2026 |
ENGR Engineering Final
|
|
Partial Pass |
Okay to apply for Level 4 TCO. Site is Almost complete. Stabilized DG sidewalk on west side will be done today and other sidewalk panels at Cleanouts is poured. Reschedule this inspection when complete. |
| 10/01/2026 |
ENGR Engineering Final
|
|
Passed |
|