Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Parcel: 13815015C


Addresses:

6675 S 12TH AV


Inspection Status: Partial Pass

Inspection History: COT - HCBU - Masonry Pregrout 

Permit Number - TC-COM-1224-02387

Inspection Description - COT - HCBU - Masonry Pregrout 

Inspection Status - Partial Pass

Date Description Inspector Results Comments
09/15/2025 COT - HCBU - Masonry Pregrout  Partial Pass 9-15-25: reinforcement for elevator shaft walls verified per plans-okay to grout 1st lift at 4'.
09/17/2025 COT - HCBU - Masonry Pregrout  Partial Pass 9-17-25: reinforcement on elegy shaft walls verified per plans. Okay to grout 2nd lift at 8'
09/19/2025 COT - HCBU - Masonry Pregrout  Canceled 9-19-25: canceled by contractor.
09/22/2025 COT - HCBU - Masonry Pregrout  Partial Pass 9-22-25: reinforcement for elevator shaft walls verified per plans. Okay to grout 3rd lift at 16'.
Note: a copy of your 3rd party inspector is required for our records. Please provide blow outs/ cleanouts every 2' horizontally to verify reinforcement cells are fully grouted.
09/23/2025 COT - HCBU - Masonry Pregrout  Partial Pass 9-23-25: reinforcement for elevator shaft walls verified per plans-okay to grout 4th lift at 24'. Additionally, I verified the grout at each blow out from 8'-to 16' and a copy of the 3rd party inspector's report from 9/22/25 was added onto the portal.
09/24/2025 COT - HCBU - Masonry Pregrout  Partial Pass 9-24-25: reinforcement per plan. Okay to grout 5th lift at 28'.
09/25/2025 COT - HCBU - Masonry Pregrout  Passed 9-25-25: reinforcement at elevator shaft walls verified per plans-top out at 34'.