Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Masonry Pregrout
Permit Number - TC-COM-1224-02387
Inspection Description - COT - HCBU - Masonry Pregrout
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/15/2025 | COT - HCBU - Masonry Pregrout | Partial Pass | 9-15-25: reinforcement for elevator shaft walls verified per plans-okay to grout 1st lift at 4'. | |
| 09/17/2025 | COT - HCBU - Masonry Pregrout | Partial Pass | 9-17-25: reinforcement on elegy shaft walls verified per plans. Okay to grout 2nd lift at 8' | |
| 09/19/2025 | COT - HCBU - Masonry Pregrout | Canceled | 9-19-25: canceled by contractor. | |
| 09/22/2025 | COT - HCBU - Masonry Pregrout | Partial Pass | 9-22-25: reinforcement for elevator shaft walls verified per plans. Okay to grout 3rd lift at 16'. Note: a copy of your 3rd party inspector is required for our records. Please provide blow outs/ cleanouts every 2' horizontally to verify reinforcement cells are fully grouted. |
|
| 09/23/2025 | COT - HCBU - Masonry Pregrout | Partial Pass | 9-23-25: reinforcement for elevator shaft walls verified per plans-okay to grout 4th lift at 24'. Additionally, I verified the grout at each blow out from 8'-to 16' and a copy of the 3rd party inspector's report from 9/22/25 was added onto the portal. | |
| 09/24/2025 | COT - HCBU - Masonry Pregrout | Partial Pass | 9-24-25: reinforcement per plan. Okay to grout 5th lift at 28'. | |
| 09/25/2025 | COT - HCBU - Masonry Pregrout | Passed | 9-25-25: reinforcement at elevator shaft walls verified per plans-top out at 34'. |