Inspection History Details
Inspection Status: Re-inspection required
Inspection History: COT - HCME - Mechanical Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/23/2026 | COT - HCME - Mechanical Final | Re-inspection required | 7-23-26: building final at room's 320-add insulation to hot copper side of water heater and missing panel schedule, missing shower head. 319-same, 314-same, 315-missing shower head, panel schedule and insulation at hot copper line of water heater, 318-missing electrical cover at kitchen receptacle, missing panel schedule, and insulation at hot copper line of water heater, 317-missing insulation to hot leg of water heater, shower head and panel schedule, 316-missing stove, shower head, panel schedule and insulation to hot leg of copper at water heater. Note: exterior mechanical was not inspected. |
|
| 07/27/2026 | COT - HCME - Mechanical Final | Partial Pass | 7-27-26: verified MEP's ( diffuser/light) at 2nd floor corridor by elevator. Finals at South-wing Rooftop- missing permanent labeling at disconnects. Disconnect labels shall identify purpose and circuit, complete UV taping of HVAC line sets and paint all PVC | |
| 07/28/2026 | COT - HCME - Mechanical Final | Re-inspection required | 7-28-26: 313-kitchen hood exhaust must be smooth, 311, 324, 312, 322, 321, 323. Install shackles at panel breakers on each unit for water heater. Reinspected units 314-320-install shackles for each water heater breaker at panels, install smooth kitchen exhausts-see 1503.3 of the 2018 IRC for details. Unit 328 ADA-vertical grab bar missing at shower and at side wall of water closet, smooth exhaust required at kitchen exhaust, switch light improperly wired at kitchen, shackle required at water heater breaker. See 1106.1.1.1 for # of required roll in showers and tubs. | |
| 07/30/2026 | COT - HCME - Mechanical Final | Canceled | 7-30-26: canceled by contractor. | |
| 08/06/2026 | COT - HCME - Mechanical Final | Partial Pass | 8/6/2026 Partial pass. All corrections were made. No new items needed. 308,309,310,325,326,327,301,302,303,304,305,306,307. Approved. | |
| 08/07/2026 | COT - HCME - Mechanical Final | Partial Pass | 8-7-26: electrical, mechanical, plumbing & building finals at rooms 217, 216, 215, 218, 219, 214, 220 approved. | |
| 08/10/2026 | COT - HCME - Mechanical Final | Partial Pass | Partial pass 221,222,223,212, 224, 213 anti tip loose, GFCI laundry area 211 needs GFCI in laundry |
|
| 08/11/2026 | COT - HCME - Mechanical Final | Partial Pass | 8-11-26: 1st floor corridor- seal all penetrations, secure low voltage wires, add knockout to above ceiling junction box and install missing lid, tape all tears to flex. Finals at Room's 225, 209, 208, 226, 227 approved. | |
| 08/12/2026 | COT - HCME - Mechanical Final | Partial Pass | 8-12-26: finals for units 210, 202, 207, 206,203, 204, 205 approved. Above ceiling MEP's 1st floor corridor approved. | |
| 08/18/2026 | COT - HCME - Mechanical Final | Partial Pass | 8-18-26: mechanical final at room's 117, 116, 118, 115, 119, 114, 120 approved. | |
| 08/19/2026 | COT - HCME - Mechanical Final | Partial Pass | 8-19-26: mechanical final at room's 121, 122, 113, 123, 112, 124, 111 approved. | |
| 08/20/2026 | COT - HCME - Mechanical Final | Partial Pass | 8/20/26 127 missing doorbell strobe, 126 missing light switch in bedroom Passed 108,109, 110, 125 |
|
| 08/21/2026 | COT - HCME - Mechanical Final | Partial Pass | 8-21-26: finals for room's 102, 107, 103, 106, 104, 105 approved. | |
| 08/25/2026 | COT - HCME - Mechanical Final | Partial Pass | 8-25-26: re-inspect's for 118, 119, 120, 121, 123, 127, 3rd floor corridors, equipment room, game, maintenance room-need access to panel, water heater room-verify shackle at panel, laundry room-install a gfci receptacle at north wall. | |
| 08/26/2026 | COT - HCME - Mechanical Final | Partial Pass | 8-26-26: 3rd floor laundry room, 2nd floor equipment room, fitness room, maintenance room, corridor, trash, equipment, laundry room approved. | |
| 09/02/2026 | COT - HCME - Mechanical Final | Partial Pass | 9/2/26 328, 201, 228, 101,, 127, 128, type a Ada approved.switch installed in 126. Pending type b grab bars at tubs | |
| 09/04/2026 | COT - HCME - Mechanical Final | Re-inspection required | 9-4-26: romex at the rooftop disconnects are not allowed per NEC/ 334.12. Secure HVAC line sets within 12" of an outlet box, junction box cabinet, or fitting. Line sets 6' and longer must be secured by a listed means of support at 3' intervals. | |
| 09/15/2026 | COT - HCME - Mechanical Final | Partial Pass | 9/15/26: Common areas-3rd floor trash, 1st floor community room-Counter top receptacle not ADA compliant-25" maximum reach. 1st floor trash room, storage room-receptacle cover, secure conduit, seal penetration, maintenance room-fire caulk all above ceiling floor chase at each floor, 1st floor bathrooms-missing vertical bar, manager's office-missing light switch receptacle cover. Mechanical final at rooftop approved and at listed above common areas. | |
| 09/16/2026 | COT - HCME - Mechanical Final | Canceled | 9/16/26: canceled by contractor. | |
| 09/17/2026 | COT - HCME - Mechanical Final | Partial Pass | 9/17/26: ADA grab bars for unit's 227, 202, 327, 301, 302 approved. Corrections made at common areas. | |
| 09/25/2026 | COT - HCME - Mechanical Final | Passed |