| 01/30/2026 |
COT - HCBU - Building Above Ceiling |
|
Partial Pass |
1-30-26: 2nd floor soffit framing inspection from stairwell to south and & east along corridor approved. 0kay to drywall progress areas-minus mechanical at south corridor. |
| 02/02/2026 |
COT - HCBU - Building Above Ceiling |
|
Partial Pass |
2-2-26: 2nd floor soffit framing north of stairwell. Okay to cover progress areas. |
| 04/08/2026 |
COT - HCBU - Building Above Ceiling |
|
Partial Pass |
4-8-26: Framing/MEP's above ceiling at maintenance shop approved. Okay to cover ceiling- we will inspect in-wall/penetrations at a later date. |
| 11/10/2025 |
COT - HCBU - Building Above Ceiling |
|
Re-inspection required |
11-10-25: room's 317-straps on ductwork every 10', 316-wall cap, 318 add supports to where dryer exhaust is off sprinkler, 315-dryer/bathroom exhaust vent off sprinkler. Check remainder of units and reschedule. |
| 11/17/2025 |
COT - HCBU - Building Above Ceiling |
|
Partial Pass |
11-17-25: Mechanical & DWV supports above ceiling for room's 317, 316, 315, 318, 319, 314, 320, C09, 321, 313, 322, 312, 323, 324, 311. Okay to spray foam 10" above ceiling. |