Permit: TC-COM-1224-02366

Parcel: 137073210


Addresses:

4945 S LIBERTY AV

Inspection Status: Not Ready

Inspection History: COT - HCME - Mechanical Progress 

Date Description Inspector Results Comments
03/19/2026 COT - HCME - Mechanical Progress  Not Ready Fire caulk all penetrations above ceiling throughout firewalls. 3/19/2026
05/11/2026 COT - HCME - Mechanical Progress  Partial Pass 5-11-26: mechanical/electrical/plumbing at the interior of unit's B114, B115, B116, B213, B214, B215, B216 approved for a Level 4 TCO.
NOTE: exterior condensers/labeling of disconnects/proper installation of refrigerant lines and sealing at disconnects must still be inspected. Waiting on RFI approval and contractor to schedule inspections.
05/13/2026 COT - HCME - Mechanical Progress  Partial Pass 5-13-26: MEP's together with mechanical, electrical, and plumbing finals for Unit's B110 & B112 approved. Exterior HVAC will be inspected at a later date.
06/02/2026 COT - HCME - Mechanical Progress  Partial Pass 6-2-26: mechanical, electrical, & plumbing finals for unit's c113 & c116 approved.
06/12/2026 COT - HCME - Mechanical Progress  Partial Pass 6-12-26: Electrical, mechanical, plumbing finals for C104, C107, C214, C215, C216, C213 approved. Okay to apply to for a Level 4 TCO.
06/23/2026 COT - HCME - Mechanical Progress  Not Ready 6.23.26
A108, C203, C204, C206, C207.
1. Condensers are too close to each other.
2. Support expansion tanks on water heater
3. Pending install of heat strips