Permit: TC-COM-1224-02366

Parcel: 137073210


Addresses:

4945 S LIBERTY AV

Inspection Status: Partial Pass

Inspection History: COT - HCPL - Plumbing Final 

Date Description Inspector Results Comments
03/24/2026 COT - HCPL - Plumbing Final  Partial Pass 3-24-26: B102-Pending installation of ADA shower seats & shower liner/p-trap test.
04/01/2026 COT - HCPL - Plumbing Final  Partial Pass 4/1/26: All issues listed above corrected. Pending electrical corrections at kitchen circuits per A117.1, pending correction at HVAC refrigerant lines and electrical whips. Revision required for HVAC system upsized to 2 ton (plans and Manual J require 1.5Ton)
04/07/2026 COT - HCPL - Plumbing Final  Partial Pass 4-7-26: Building final for Unit C119 approved.
Note: will conduct a walk through of exterior items to include, A/C disconnect labeling/sealing, refrigerant lines, and revision for 1.5 to 2 ton unit.
04/23/2026 COT - HCPL - Plumbing Final  Re-inspection required 4/23/26: Note: cannot occupy prior to an egress plan and a barrier from construction to the public. (Tenants) TCO will be required along with other items prior to occupancy. Fire-inspector approval required prior to issuance of TCO.
04/30/2026 COT - HCPL - Plumbing Final  Re-inspection required 4-30-26: plumbing final on A206, A204, A203, A201, A202 approved. Unit's B201, B202, B204-grab bar behind toilet must be a minimum of 36".
Note: cannot occupy prior to an egress plan and a barrier from construction to the public. (Tenants) TCO will be required along with other items prior to occupancy. Fire-inspector approval required prior to issuance of TCO.
05/04/2026 COT - HCPL - Plumbing Final  Partial Pass Partial pass. B205,B206,B207,B208,B209. Approved. 5/4/2026
05/06/2026 COT - HCPL - Plumbing Final  Partial Pass Partial pass. B210, B211, B212. Approved 5/6/2026
05/08/2026 COT - HCPL - Plumbing Final  Canceled 5-8-26: canceled by contractor.
05/12/2026 COT - HCPL - Plumbing Final  Partial Pass 5-12-26: MEP's together with Electrical, Plumbing, & Mechanical Finals at UNIT's B111 & B113 approved. This does not include Mechanical on the exterior which will be inspected when ready.
05/14/2026 COT - HCPL - Plumbing Final  Partial Pass 5-14-26: mechanical, electrical, plumbing finals for Unit's B107 & B109 approved.
05/20/2026 COT - HCPL - Plumbing Final  Partial Pass 5-20-26: mechanical, electrical, plumbing finals for Units B108, B106, B105, B104, A102 approved. Okay to apply for a Level 4 TCO.
05/27/2026 COT - HCPL - Plumbing Final  Partial Pass 5-27-26: plumbing, electrical, mechanical finals for Unit's A101- provide a shower liner/pan test with 2" of water above the top of threshold, A110, A109-not ready, A111 -not ready. Okay to apply for a Level 4 TCO on Unit 110.
05/28/2026 COT - HCPL - Plumbing Final  Partial Pass 5/28/2026 A101, A103, A109, A111, A113 approved. A12 not ready.
06/01/2026 COT - HCPL - Plumbing Final  Partial Pass 6-1-26: plumbing, electrical, mechanical finals for Unit's C114 & C115 approved.
06/03/2026 COT - HCPL - Plumbing Final  Partial Pass 6-3-26: plumbing, electrical, mechanical final's for C117 & C112 approved. Schedule TCO inspection at your convenience.
06/04/2026 COT - HCPL - Plumbing Final  Partial Pass 6-4-26: plumbing, electrical, mechanical finals for unit's C106 & C118 approved.
06/08/2026 COT - HCPL - Plumbing Final  Partial Pass 6-8-26: C109& C102 electrical, mechanical, and plumbing finals approved.
06/09/2026 COT - HCPL - Plumbing Final  Partial Pass 6-9-26: Electrical, mechanical, and plumbing finals for C103 & C108 approved.
06/15/2026 COT - HCPL - Plumbing Final  Partial Pass 6-15-26: plumbing final for room's C212 & C217 approved.
06/18/2026 COT - HCPL - Plumbing Final  Partial Pass 6-18-26: finals for Units C219, C210, C201, C218 approved.
06/23/2026 COT - HCPL - Plumbing Final  Partial Pass 6-23-26: C203,C206, C207, C204.
08/17/2026 COT - HCPL - Plumbing Final  Partial Pass 8/17/26 2nd floor c wing women's restroom, b wing both restrooms c wing kitchen