Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - TCO
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/04/2026 | COT - HCBU - TCO | Partial Pass | B101, B102, C105, C111, C119, B213, A209, A211, A212, A210, A208, A207, A205, A206, A204, A203, A201, A202, B201, B202, B204, B203, B205, B206, B208. Okay for level 4 TCO. 5/4/2026 | |
| 05/06/2026 | COT - HCBU - TCO | Partial Pass | Partial pass. B210, B211, B212. Approved. Okay for level 4 TCO. 5/6/2026 | |
| 05/11/2026 | COT - HCBU - TCO | Partial Pass | 5-11-26: mechanical/electrical/plumbing at the interior of unit's B114, B115, B116, B213, B214, B215, B216 approved for a Level 4 TCO. NOTE: exterior condensers/labeling of disconnects/proper installation of refrigerant lines and sealing at disconnects must still be inspected. Waiting on RFI approval and contractor to schedule inspections. |
|
| 05/20/2026 | COT - HCBU - TCO | Partial Pass | 5-20-26: mechanical, electrical, plumbing finals for Units B108, B106, B105, B104, A102 approved. Okay to apply for a Level 4 TCO. | |
| 05/27/2026 | COT - HCBU - TCO | Partial Pass | 5-27-26: okay to apply for a Level 4 TCO on Unit 110. | |
| 05/29/2026 | COT - HCBU - TCO | Partial Pass | Partial pass. Finals for Units A104, A112, A113 approved. Okay for level 4 TCO 5/29/2026 | |
| 06/02/2026 | COT - HCBU - TCO | Partial Pass | 6-2-26: mechanical, electrical, & plumbing finals for unit's c113 & c116 approved. Okay to apply for a Level 4 TCO. | |
| 06/04/2026 | COT - HCBU - TCO | Partial Pass | 6-4-26: plumbing, electrical, mechanical finals for unit's C106 & C118 approved. Okay to apply for a Level 4 TCO. | |
| 06/08/2026 | COT - HCBU - TCO | Partial Pass | 6-8-26: C109& C102 electrical, mechanical, and plumbing finals approved. Okay to apply for a Level 4 TCO. |