Inspection Status: Partial Pass
Inspection History: ENGR Engineering Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/03/2026 | ENGR Engineering Final | Partial Pass | Engineering Final for all units in Building A and Building B is passed, these units are safe and complete (A101-113, A201-213, B101-116, B201-216). 7 units in building C; C105, C111, C113, C114, C115, C116, C119 are okay to apply for TCO level 4. Ingress and egress must be maintained for these units for the duration of the project and all work must be confined to the unoccupied units. |
|
| 11/10/2026 | ENGR Engineering Final | Re-inspection required | Submit as-built showing elimination of pedestrian gate at enclosure due to accessibility issues. Add handrails ay southwest ramp per field discussion. Satisfy outstanding conditions. |