Inspection Status: Canceled
Inspection History: COT - HCPL - Plumbing Progress
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/11/2026 | COT - HCPL - Plumbing Progress | Canceled | 3-11-26: canceled | |
| 03/19/2026 | COT - HCPL - Plumbing Progress | Not Ready | Fire caulk all penetrations above ceiling throughout firewalls. 3/19/2026 | |
| COT - HCPL - Plumbing Progress | Canceled | 4-3-26: canceled. | ||
| 05/11/2026 | COT - HCPL - Plumbing Progress | Partial Pass | 5-11-26: mechanical/electrical/plumbing at the interior of unit's B114, B115, B116, B213, B214, B215, B216 approved for a Level 4 TCO. NOTE: exterior condensers/labeling of disconnects/proper installation of refrigerant lines and sealing at disconnects must still be inspected. Waiting on RFI approval and contractor to schedule inspections. |
|
| 05/13/2026 | COT - HCPL - Plumbing Progress | Partial Pass | 5-13-26: MEP's together with mechanical, electrical, and plumbing finals for Unit's B110 & B112 approved. Exterior HVAC will be inspected at a later date. |