Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCME - Mechanical Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/24/2026 | COT - HCME - Mechanical Final | Partial Pass | 3-24-26: mechanical final approved. | |
| 04/01/2026 | COT - HCME - Mechanical Final | Partial Pass | 4/1/26: All issues listed above corrected. Pending electrical corrections at kitchen circuits per A117.1, pending correction at HVAC refrigerant lines and electrical whips. Revision required for HVAC system upsized to 2 ton (plans and Manual J require 1.5Ton) | |
| 04/07/2026 | COT - HCME - Mechanical Final | Partial Pass | 4-7-26: Building final for Unit C119 approved. Note: will conduct a walk through of exterior items to include, A/C disconnect labeling/sealing, refrigerant lines, and revision for 1.5 to 2 ton unit. |
|
| 04/21/2026 | COT - HCME - Mechanical Final | Partial Pass | A213,A209 completed. Note: cannot occupy prior to an egress plan and a barrier from construction to the public. (Tenants) TCO will be required along with other items prior to occupancy. 4/21/2026 | |
| 04/30/2026 | COT - HCME - Mechanical Final | Re-inspection required | 4-30-26: pending RFI approval for 1.5 ton -2ton units for rooms A206, A204, A203, A201, A202, B201, B202, B204. Reschedule when RFI has been approved and we will conduct a mechanical final verifying , A/C disconnect labeling/sealing, refrigerant lines. | |
| 05/04/2026 | COT - HCME - Mechanical Final | Partial Pass | Partial pass. B205,B206,B207,B208,B209. Approved. 5/4/2026 | |
| 05/06/2026 | COT - HCME - Mechanical Final | Partial Pass | Partial pass. B210, B211, B212. Approved 5/6/2026 | |
| 05/08/2026 | COT - HCME - Mechanical Final | Canceled | 5-8-26: canceled by contractor. | |
| 05/12/2026 | COT - HCME - Mechanical Final | Partial Pass | 5-12-26: MEP's together with Electrical, Plumbing, & Mechanical Finals at UNIT's B111 & B113 approved. This does not include Mechanical on the exterior which will be inspected when ready. | |
| 05/14/2026 | COT - HCME - Mechanical Final | Partial Pass | 5-14-26: mechanical, electrical, plumbing finals for Unit's B107 & B109 approved. | |
| 05/20/2026 | COT - HCME - Mechanical Final | Partial Pass | 5-20-26: mechanical, electrical, plumbing finals for Units B108, B106, B105, B104, A102 approved. Okay to apply for a Level 4 TCO. | |
| 05/27/2026 | COT - HCME - Mechanical Final | Partial Pass | 5-27-26: plumbing, electrical, mechanical finals for Unit's A101- provide a shower liner/pan test with 2" of water above the top of threshold, A110, A109-not ready, A111 -not ready. Okay to apply for a Level 4 TCO on Unit 110. | |
| 05/28/2026 | COT - HCME - Mechanical Final | Partial Pass | 5/28/2026 A101, A103, A109, A111, A113 approved. A12 not ready. | |
| 06/01/2026 | COT - HCME - Mechanical Final | Partial Pass | 6-1-26: plumbing, electrical, mechanical finals for Unit's C114 & C115 approved. Note: in order to occupy these rooms you need to schedule a TCO inspection and apply for a Level 4 TCO. |
|
| 06/03/2026 | COT - HCME - Mechanical Final | Partial Pass | 6-3-26: plumbing, electrical, mechanical final's for C117 & C112 approved. Schedule TCO inspection at your convenience. | |
| 06/04/2026 | COT - HCME - Mechanical Final | Partial Pass | 6-4-26: plumbing, electrical, mechanical finals for unit's C106 & C118 approved. | |
| 06/08/2026 | COT - HCME - Mechanical Final | Partial Pass | 6-8-26: C109& C102 electrical, mechanical, and plumbing finals approved. | |
| 06/09/2026 | COT - HCME - Mechanical Final | Partial Pass | 6-9-26: Electrical, mechanical, and plumbing finals for C103 & C108 approved. |