Inspection History Details
Inspection Status: Passed
Inspection History: COT - HCEL - Electrical Intermediate
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/26/2024 | COT - HCEL - Electrical Intermediate | Passed | This inspection is approved per contractor responsibility letter. | |
| 08/03/2023 | COT - HCEL - Electrical Intermediate | Not Ready | 8/3/23: Roof not dried in, not ready for intermediates,insulation, or wallboard. | |
| COT - HCEL - Electrical Intermediate | Partial Pass | |||
| 10/26/2023 | COT - HCEL - Electrical Intermediate | Not Ready | 8/3/23: Roof not dried in, not ready for intermediates,insulation, or wallboard. 8/9/23 In wall ok to cover, 10/12/23 - NR for clearance, missing grounding, bonding, no buss bars or primary conductors present for 3phase connections 10/26/23: NR for Clearance, missing second ground rod, no primary conductors missing present for 3phase connections, missing 2 200 amp breakers and revision needs to be sent in for change in 800amp to 600amp main breaker. |