Inspection Status: Partial Pass
Inspection History: ENGR Engineering Final
| Date |
Description |
Inspector |
Results |
Comments |
| 04/05/2024 |
ENGR Engineering Final
|
|
Partial Pass |
Vehicular entrance does not meet plan specifications. Period. |
| 04/15/2024 |
ENGR Engineering Final
|
|
Passed |
this inspection was for the bollards protecting the electrical gate access panel. the gate and any other issues that require inspection need to contact Building, spoke with Pete Lee with COT to confirm. this inspection “passed” was confirmed with Mr. David Roberts. |
| 04/16/2024 |
ENGR Engineering Final
|
|
Passed |
this inspection was for the bollards protecting the electrical gate access panel. the gate and any other issues that require inspection need to contact Building, spoke with Pete Lee with COT to confirm. this inspection “passed” was confirmed with Mr. David Robert’s. |