Inspection Status: Partial Pass
Inspection History: COT - CSOL - Electrical Intermediate Solar Project
| Date |
Description |
Inspector |
Results |
Comments |
| 06/16/2026 |
COT - CSOL - Electrical Intermediate Solar Project |
|
Partial Pass |
Partial pass. Verified wire size and termination of wires in all 5 inverters. All torqued to spec. Verified duct seal at entries of raceways. All approved per plan. Pending completion of CT can. Schedule intermediate once completed along with finals. 6/16/2026 |
| 06/18/2026 |
COT - CSOL - Electrical Intermediate Solar Project |
|
Partial Pass |
6-18-26: electrical intermediates approved. Okay to energize-DGL clearance provided to TEP after hours at 2:58AM. Contractor will upload torque specifications to the city for review. |
| 07/22/2026 |
COT - CSOL - Electrical Intermediate Solar Project |
|
Passed |
TEP CLEARANCE: DGL, for CT-01; called in at 11:55. |
| 07/31/2026 |
COT - CSOL - Electrical Intermediate Solar Project |
|
Passed |
|